Bexley Primary School Expansions

Project Details

Expansion by one form of entry to six primary schools

Client – London Borough of Bexley

Services – Project Manager, Quantity Surveyor and CDM Co-ordinator

Value – £21,700,000

The primary school expansion programme for Bexley Council involved the expansion by one form of entry at six primary schools – during the initial feasibility studies it was agreed that the designs for each school would be based on the same outline layout and design and the same specification for finishes, sanitary fittings etc.

The designs were signed off by all parties at three key stages:

  • Stage 1 – General Arrangement – Design Freeze
  • Stage 2 – Interim Works – the works required to be implemented prior to the start of the next academic year
  • Stage 3 – Detailed design and choice of colours

It was made clear that any changes made after each stage sign off would fall outside the scope of the contract and may not be implemented – or if implemented corresponding savings would have to be achieved. By adopting the above procedure we have achieved Standardisation of depths and Economies in buying gains, together with achieving consistency of approach and methodology, etc.

This project has provided schools with modern, sustainable buildings and teaching facilities, and the buildings have been constructed using Cross Laminated Timber with sustainability in mind, ensuring low maintenance costs and value for money throughout.

All of the schools remained open during the work, with a number of the schools requiring the provision of temporary accommodation. Extensive enabling works were required at all of the sites.

Comments are closed.

Content © Playle & Partners 2020

Tel: 020 8300 6811 Email: sidcup@playleandpartners.co.uk Registered Office: Crest House, 138 Main Road, Sidcup, Kent, DA14 6NY
Playle & Partners is a Limited Liability Partnership registered in England under no. OC317809.
A list of members is open to inspection at our offices.